Earned Value Analysis
- Budget at completion ($BAC$): total budget for the project
- Planned value ($PV$): budgeted cost of work planned
- Earned value ($EV$): budgeted cost of work performed
- Actual cost ($AC$): actual cost for the completed work
Schedule
The project running behind schedule if the value produced is less than the value planned ($EV < PV$).
- Schedule variance: $SV = EV – PV$
- Schedule performance index: $SPI = EV /PV$
Both values are lower than zero if the project is running behind schedule.
Cost
The project running over budget if the value produced is less than the cost ($EV < AC$).
- Cost variance: $CV = EV – AC$
- Cost performance index: $CPI = EV/AC$
Both values are lower than zero if the project is spending more than planned.
Estimations
Perform an estimation of the budget at completion of the project using some assumptions:
- continue to spend at the same rate (same CPI)
- continue to spend at the baseline rate
- continue at the same cost and schedule performance index (same CPI and SPI)
For example the cost estimate at completion can be:
- If we continue to spend at the same rate $EAC = BAC/CPI$
- If we continue to spend at the original rate $EAC = AC + (BAC – EV)$
- Both CPI and SPI influence the remaining work: $EAC = \frac{AC + (BAC – EV)}{(CPI \times SPI)}$
Past exams exercises
2020 09 04 Q3 (3 points)
A project has been setup to build an application composed by four software components. The budget assigned to the project is 14000 euros. The project costs are the following:
- 2000 euros for the initiating phase.
- 1000 euros for the planning phase.
- 9000 euros for the executing phase: 2000 euros for the first component, 3000 for the second, 2000 for the third, 2000 for the last.
- 2000 euros for the project closing.
The schedule is the following:
A planned review is provided after 60 days from the project start; the project manager calculates the following parameters according to the Earned Value Analysis:
- Earned Value is 7500 euros.
- Actual Cost is 6000 euros.
As PM of the project please answer the following questions:
- Inform the stakeholders about the situation of the project in terms of schedule and cost.
- Estimate the budget at completion ($EAC$) of the project considering the following two options:
- Continue to spend at the actual rate.
- Continue to spend at the original rate.
SOLUTION
From the project definition:
- $BAC = 14000$
- $PV = 8000$ (after 60 days we should have completed the software component 2)
- We are using less budget than planned since the value produced is greater than the cost $EV > AC$ ($7500 > 6000$) but we are behind in schedule since the value produced is less than the value planned $EV < PV$ ($7500 < 8000$).
- The cost performance index of the running project is $CPI = EV/AC = 1.25$.
- Using the actual rate $EAC = BAC/CPI = 14000/1.25 = 11200 €$
- Continuing at the original rate $EAC = AC + (BAC – EV) = 6000 + (14000-7500) = 12500 €$
2019 02 01 Q3 (3 Points)
A project has been set up to build an application composed of three software components. The budget assigned to the project is 10000 euros. At a planned review the project manager (PM) calculates the following parameters according to the Earned Value Analysis:
- Earned Value ($EV$) is 800 euros.
- Planned Value ($PV$) is 1500 euros.
- Actual Cost ($AC$) is 1000 euros.
As PM of the project please answer to the following questions:
- Inform the stakeholders about the situation of the project in terms of schedule and cost.
- Estimate the budget at completion ($EAC$) of the project considering the following two options:
- The project will progress spending at the actual rate.
- The project will progress spending at the original rate.
SOLUTION
- The project is running over budget because the value produced is less than the cost ($EV < AC$); in addition, it is running behind schedule because the value produced is less than the value planned ($EV < PV$).
- The cost performance index of the running project is $CPI = EV/AC = 0.8$
- Using the actual rate $EAC = BAC/CPI = 10000/0.8 = 12.500 €$
- Continuing at the original rate $EAC = AC + (BAC – EV) = 1000 + (10000-800) = 10200 €$
